- Atlantik Confidence – Expert Opinion
- Bulk Jupiter – Expert Opinion
- Decomissioning of Large Northern North Sea Platform
- Flinterstar Wreck Removal
- Heavy-Lift Transshipment Base Facility, Port of Burgas Upgrade
- Heavy-Lift Transshipment Base Facility, Port of HaminaKotka Upgrade
- Independent Witness for Experimental Jack-up Operations
- Project Cargo Risk Management Consultancy
- Sarens NV – Sundsvall Bridge – Liftpontoon
- Seafastening and Grillage Design
- Ship Speed Trial Verification
- Thornton Bank Wind Farm Phases 2 & 3
Seafastening and Grillage Design
Location:
Tarragona, Spain to Antwerp, Belgium
Our Role:
Transportation Analysis
Grillage & Seafastening design & verification
Project Description:
At the request of our client, we were asked to provide a broad range of marine services to support the multi-shipment transportation of a large number of modules including pre-assembled pipe racks, pre-assembled processing units and towers from the East Coast of Spain, across the Bay of Biscay to Belgium.
The scope of work undertaken by Mwaves included:
- Motions analyses;
- Design loading conditions;
- Grillage and seafastening detailed design;
- Tug specification;
- Barge strength analyses;
- Load-out/Load-in ballasting calculations.
As the project required close collaboration with our client and a detailed understanding of the dynamic project, Mwaves dedicated an engineer who spent large amounts of time at the clients office along side the clients project team. Additional resources and input was provided from our team of naval architects, structural engineers and master mariners.